width50%

Core Services Status

Status
colourGreen
titleCALENDAR
- Department Calendar Services.

Status
colourGreen
titleCERBERUS
- /opt/local and shared data services.

Status
colourGreen
titleDHCP
- Wired DHCP services for the department.

Status
colourGreen
titleDOCUSHARE
- DocuShare database.

Status
colourGreen
titleFTP
- Anonymous FTP services.

Status
colourGreen
titleHYDRA
- HET Observing Support

Status
colourGreen
titleIDL
- IDL License server

Status
colourGreenYellow
titleMAIL
- Astro mail services

Status
colourGreen
titleMATHEMATICA
- Mathematica License server

Status
colourGreen
titlePRINTERS
- Department Printer services

Status
colourGreenYellow
titleWEBMAIL
- Webmail services

Status
colourGreen
titleWEBSEVERS
- Department websites and related services

 

Column
width50%

Individual Printer Status

If Printers under Core Services Status is Green, then the printer queue is active.  Below lists the public printers and their individual status in case one of them fail.

Status
colourGreen
titleCopiers
- All Ricoh copiers

Status
colourGreen
titleDW
- Department color

Status
colourGreen
titleLASER13
- 13th floor black and white

Status
colourGreen
titleLASER15
- 15th floor black and white

Status
colourGreen
titleLASER16
- 16th floor black and white

 

 

Unscheduled Maintenance

  • 22 August @12:45 PM Stop, Refresh and Restart mail services to clear out zombie processes. 

Planned Maintenance

 

  • 24 July @10:48am Resuming normal operations
  • 24 july @7:00am -12:00pm all major service will be offline for some period during this maintenance window
  • 15 July @ 12:45 PM - astro email  back online.
  • 15 July @ 12:15 PM - astro email (& thus webmail) SSL Security Certificates Update Click on Core Services Status above for grisly details
  • 13 July @ 5:00 PM - astro email (& thus webmail) SSL Security Certificates Update: :Click on Core Services Status above for grisly details.

    The SSL security certificates must be updated for mail services on astro to provide compatibility with utexas.edu mail services. SSL Certificate configuration continues to be a recondite undertaking with a plethora of convoluted methodologies and a poverty of guidance. In short, this may take awhile.

    5:00 PM astro email and webmail will be taken off-line for the SSL certificate updates.


  • 1 May 2015 @ 11:30  - In preparation for upcoming rewiring of our switch closet in RLM, there will be work performed to clear off a switch to use in the refit.  What this means for the user base is that there is a possibility that the connections in your rooms may be momentarily lost as connections are rerouted.  This is a joint project with CNS and is needed to get the refit that the closet desperately needs.  If you experience any lasting problems with your computer or phone connections, please send an email to helpdesk.  None of our core services are planned to be down due to this maintenance.  This only effects connections to individual offices.
  • 13 May @ 5:30 PM - astro and our other Solaris servers, ftp and gemini, will be rebooted at 5:30 PM today to apply maintenance and security patches. The updates have already been installed but require a reboot to be applied. The following services will be affected and be offline while the system are rebooting which hopefully will take less than 15 minutes.
    • astro email
    • webmail