This page will be frequently updated to include answers to questions that are being sent to BSoM staff and administration. In addition to the information on this page, here are some links to College and University-level sources:
...
Status of Renovations and Maintenance Work
MRH
...
Currently, the electric prep work that was scheduled for the week of Spring Break in MRH and MBE has been canceled. As of today, the abatement work that was happening in MRH basement is still happening next week (just not the power shutdown) and the HVAC will be shutdown Tuesday-Thursday “if Zone is available to shut them down”.
...
The MRH electrical and HVAC renovation will likely be moved up. The current target date to turn off power and air-conditioning in MRH is April 27. Cobra Piano Movers will be moving several grand pianos within the next three weeks from faculty studios with windows, performance halls, and some classrooms. Russell and Page will coordinate to prepare MRH offices for the shutdown while faculty and staff work remotely.
Jessen
The lighting renovation at Jessen is being has been completed this week. We will be fully functional with new lights in the hall when return to campus.
...
Resources & Deadlines for Faculty
Updated Syllabi & Course Plan
Email students in your courses by Friday, March 27 at noon with an updated syllabus along with the protocol and schedule for instruction. Complete the Course Plan for Instructional Continuity by Friday, April 3 at 5 PM.
Teaching assistants and assistant instructors, please coordinate any communications between you and your students with your supervising faculty members. Please approach students with empathy and caring.
| Anchor | ||||
|---|---|---|---|---|
|
Online Teaching Tools
If you have already worked out a different way of delivering online instruction that works for you, go for it! If you think your approach solves a common problem, please send it to Mary Ellen Poole and Jeff Hellmer for potential inclusion in a future FAQ email.
...