2016-01-08 Meeting notes

2016-01-08 Meeting notes

Date

Attendees

Goals

  • Exchange information about the DRP project
  • Discuss project management process using examples

  • Check status of the project

Discussion items

TimeItemWhoNotes
5 minutesIntroductionsMark McFarland

 

5 minutesPurpose of the ProjectMark McFarland 
3 minutesHow the Project is StructuredMark McFarland 
5 minutesReview of the Seven Phases of the ProjectElizabeth Castillo 
3 minutesTimelineElizabeth Castillo 
10 minutesReview the Project BinderElizabeth Castillo and Eric Rostetter
  • Hand outs will be distributed at each meeting IF there are changes to binder documents and will also be placed in the Wiki

10 minutesIntroduction, Phase 1 DeliverablesEric Rostetter 
3 minutesRoles and ResponsibilitiesElizabeth Castillo 
3 minutesPurpose of Weekly MeetingsElizabeth Castillo 
10 minutesSummary and Q/A

Elizabeth Castillo and Eric Rostetter

Action items

  • Elizabeth: Compile Sign-In sheet with POCs in the DRP Project Charter and make changes accordingly (see page 6 in the charter and have handouts for next meeting)
  • Eric/Elizabeth: Ensure all POCs have a UT Ready plan ready for activation of the DRP
  • Elizabeth: Make contact with POCs who were unable to make it to the 1/8/16 meeting
  • Eric/Elizabeth: Use a small unit as an example for UT Ready for live presentation at next meeting
  • Eric: Touch base with Astronomy/McDonald about needed access and changes
  • Elizabeth: Touch base with Ben Costello about assigned POC for physics

 

Attendees: POC - DRP Project

Date and time of next meeting: 1-15-2015 from 1:00pm to 2:00 pm in WCH 3.102

Group reviewed the agenda items for the DRP project and the above action items are the result of the meeting. Phase 1 will continue to Jan 22nd and next weeks meeting will answer any questions or concerns folks may have on Phase 1.