2016-01-08 Meeting notes
Date
Jan 8, 2016
Attendees
@Eric Rostetter
@Elizabeth A Castillo
Goals
Exchange information about the DRP project
Discuss project management process using examples
Check status of the project
Discussion items
Time | Item | Who | Notes |
|---|---|---|---|
5 minutes | Introductions | Mark McFarland |
|
5 minutes | Purpose of the Project | Mark McFarland |
|
3 minutes | How the Project is Structured | Mark McFarland |
|
5 minutes | Review of the Seven Phases of the Project | Elizabeth Castillo |
|
3 minutes | Timeline | Elizabeth Castillo |
|
10 minutes | Review the Project Binder | Elizabeth Castillo and Eric Rostetter |
|
10 minutes | Introduction, Phase 1 Deliverables | Eric Rostetter |
|
3 minutes | Roles and Responsibilities | Elizabeth Castillo |
|
3 minutes | Purpose of Weekly Meetings | Elizabeth Castillo |
|
10 minutes | Summary and Q/A | Elizabeth Castillo and Eric Rostetter |
|
Action items
Attendees: POC - DRP Project
Date and time of next meeting: 1-15-2015 from 1:00pm to 2:00 pm in WCH 3.102
Group reviewed the agenda items for the DRP project and the above action items are the result of the meeting. Phase 1 will continue to Jan 22nd and next weeks meeting will answer any questions or concerns folks may have on Phase 1.