Nextbreak Vehicle Documentation
https://cloud.wikis.utexas.edu/wiki/spaces/LHRSOLAR/pages/541918008
things will need to be reconsidered/redone if we switch from next gen to next break
|
Aeroshell Top SRR:
bidirectional
array area
Leads Agenda:
array optimization - how many subarrays and segments
bulkhead timeline for ptn
Critical Blockers
Dynamics Load cases
What its blocking - All dyn revalidation
Plan of action: Weight shell with corner balance, make sure all other mass properties are good and update
Get weights, cgz and cgy
Re calc weight dist, loads per wheel, dyn loads, truss solver
plan to do saturday night (11/8) after cota event
Bottom Shell Scan
What its blocking - Top shell redesign, composite design → in turn blocks mounting etc
Plan of action: scan sunday 11/9
Recad daybreak bottom shell
if we can have bounding boxes for bump brake steer that would be nice
make it usable for sims
Workday Goals
Aero, Composites
Figure out max array area → look into extensions and stuff
critical bulkheads → bulkhead reference sketch
make all init cutouts in bottom shell in cad
first iteration of ts w/ canopy cutouts and placeholder canopy in cad and 000
Array
Sub arrays → given array space do we still want/need 3
can we have panels on the side (worst case scenario)
how much layout change
start figuring out how many modules → d2 requote maybe
Dynamics
Have first iteration of all components passing and mainly finalized so that new loadcases won’t cause too much of a change (hopefully)
Make bounding boxes for bump brake steer → done before workday ideally
Fergo
frame welding timeline done by end of workday
figure out better ballast box position
Vcat/psys
lighting/camera integration
ptn
pde location (change to be better so that we can build new canopy around it) (whatever hinging issue it was)
Timeline:
11-8
Daybreak scanned
Daybreak shell recad (due before workday)
11-15
Daybreak sims
11-22
Thanksgiving
Top shell design finalized
December
12/1 Final 000 critical
12/6
put in mold order ts
12/13
Winter break
FINAL 000 + mechanisms
January
1/10
Dynamics Integration
1/17
mold received ts
1/24
1/31 Workday
Wheels down
February
Aerodynamics Integration
March Spring Break
Mechanical integration
Shell on
April Unveiling
May