Daybreak Electrical Maintenance Tasks

Board

System

Notes

Board

System

Notes

Power Board

Power Systems

What is insufficient?

  • Poor protection and filtering, Bad switching circuit

Repair Options exist?

  • A redesign should be pretty straightforward and quick to manufacture

Time

  • Honestly design all the way through working maybe like 2-3 months most. Design can probably be done in 2-3 weeks and then might need a couple iterations

New members

  • New members could be involved but if the goal is to make sure we have it working fast it may be best to just have old members handle so we get it done ASAP and new members can shadow for the next design.

Scrutineering Board

BPS

What is insufficient?

  • Fuses funny and new battery box

Repair Options exist?

  • yes should be free

Time

  • like a month

New members

  • honestly they probably can but again might just be easier to have an old member crank it out rq and then new members can work on redesigning and stuff

MPPTs

Power Gen

What is insufficient?

  • Poor documentation and they’re old

Repair Options exist?

  • Can buy

Time

  • No redesign so should be fast

New members

  • They can work on research

Contactor Driver

Power Systems

What is insufficient?

  • Stinky harnessing problems

Repair Options exist?

  • Lowkey alr redesigned need to look at and review though

Time

  • Like a month lowkey

New members

  • They could do it after we make sure the redesign works

Fan Board

BPS

What is insufficient?

  • Need to fix fan reqs for new car

Repair Options exist?

  • Yes should be easy

Time

  • Like a month

New members

  • They can work on it

Controls Board

Controls

Remove legacy hardware and fix

Ignition Switch/Dashboard

Controls

Consolidate all switches and LEDs to make harnessing to leaderboard easier

Breakout board for voltage and temperature taps

Power Systems/BPS

Not necessary but could be nice