2024-2026 Power Gen Project Timelines
Blackbody
Iteration 1’s Board & Firmware
PCB should be ready to be sent for manufacturing. Should immediately start testing after coming back from winter break.
Deadline: December 9th, 2024 (last day of class before finals and winter break)
Custom MPPT
Iteration 1’s Board & Firmware
PCB should be ready to be sent for manufacturing. Should immediately start testing after coming back from winter break.
Deadline: December 9th, 2024 (last day of class before finals and winter break)