First Workday Plan - 9/28/2024
First Workday
Notes:
Encourage them to come to the social
Task | Start time | End Time |
Everyone arrives | 9:30 | 9:45 |
Philip and Michael give a little spiel | 9:45 | 10:00 or 10:15 |
Get them in the correct Slack channels and just talk to them to make friends | 10:00 | 10:30 or 10:45 |
Subsystems presentation
Fill out interest forms | 10:30 | 11:15 |
Facilities Tour | 11:15 | 11:30 |
Take them through our softwares like BILD and Solidworks | 11:30 | 12:15 |
Lunch
| 12:30 | 2:00 |
CAD lecture | 2:00 | 3:00 or 4:00 |
CAD practice | 3:00 or 4:00 | 5:00 |