Powertrain Spring 2025 Timeline

Powertrain Spring 2025 Timeline

image-20251222-185738.png

High Level Timeline (12/16 – tentative)

 

January 31:

  • Major powertrain designs frozen

  • Segment-level testing completed

  • Battery-related outsourcing sent out

  • Interfaces and critical geometry stabilized

February 21:

  • Ventilation/ intake and exhaust manufactured

  • Battery modules manufactured

  • High-priority enclosures manufactured

    • Fuse box

    • PDE

    • Dash

    • MOCO

    • Power selector

    • Pedals

  • Tubing manufactured

  • Test loop assembled and running

March 16:

  • Segment manufacturing completed

  • Medium-priority enclosures manufactured

    • MPPT

    • Pump

    • Telemetry leader

  • Cold plate integration underway

  • Subsystem fit-ups and early integration activities begin

April 4:

  • Low-priority enclosures manufactured

    • Telemetry minions

    • Lighting

    • Canopy

  • Full battery integration underway

  • Transition to system-level testing and validation