Powertrain Spring 2025 Timeline
High Level Timeline (12/16 – tentative)
January 31:
Major powertrain designs frozen
Segment-level testing completed
Battery-related outsourcing sent out
Interfaces and critical geometry stabilized
February 21:
Ventilation/ intake and exhaust manufactured
Battery modules manufactured
High-priority enclosures manufactured
Fuse box
PDE
Dash
MOCO
Power selector
Pedals
Tubing manufactured
Test loop assembled and running
March 16:
Segment manufacturing completed
Medium-priority enclosures manufactured
MPPT
Pump
Telemetry leader
Cold plate integration underway
Subsystem fit-ups and early integration activities begin
April 4:
Low-priority enclosures manufactured
Telemetry minions
Lighting
Canopy
Full battery integration underway
Transition to system-level testing and validation