2026 Composites Manufacturing Timeline
Week 1: Jan 26-30
Composites @ Pickle → Jaden, Javi, pledges
Clean metal boards, prep for layups, cut materials (topshell bulkheads)
Aerodynamics
Canopy Mold made, reviewed (Jan 28), and finalized
Weekend 1: Jan 31
Composites: @ Rob Edwards
New members: Wheel hole cover layups
Week 2: Feb 2-6
Composites @ Pickle
cut materials for bs bulkheads
draw cut outs for bottom shell
Aerodynamics
Canopy mold finalized
tabs finalized
Weekend 2: Feb 7
Composites @ Rob Edwards
Bottom shell bulkheads layup 1
dremmel cut outs - advait dependent
Week 3: Feb 9-13
Composites @ Pickle
cut materials for bs bulkheads
mold arrival + prep
Weekend 3: Feb 14
Composites @ Rob Edwards
Bottom shell bulkheads layup 2
Livery @ ETC
send unveiling committee color scheme for decor
Week 4: Feb 16-20 (contingent on both mold arrival)
Aeroshell @ Pickle
sanding topshell mold
Composites @ Pickle
prep top shell layup materials
Weekend 4: Feb 21
Composites @ Rob Edwards
Top shell bulkhead layup 1
Chemical spray
retrieve bottomshell bulkheads
Week 5: Feb 23-27
Aeroshell @ Pickle
sanding
send out bottom shell bulkheads to be waterjet
Bottomshell Reinforcements: bulkheads and wheel cover holes be installed
Composites @ Pickle
Cut materials (top shell bulkheads)
Weekend 5: Feb 28
Composites @ Rob Edwards
Chemical spray for topshell
Top shell bulkhead layup 2
Composites @ Pickle
have finished mold + assembled (final deadline march 6)
Week 6: Mar 2-6
Aeroshell @ Pickle
Sand topshell + cut materials
Livery design finalized and internal approval (All changes made by workday)
Approved by: Advait, Kayla, Hayden, Hardhik, CR
Weekend 6: Mar 7
Composites @ Rob Edwards
top shell bulkheads retrieved, ready to waterjet
sand topshell
gel coat canopy
Livery @ ETC
by EOD, livery finalized
Week 7: Mar 9-13
Aeroshell @ Pickle
Sand topshell + cut materials
sand canopy + cut material
Composites @
Send out top shell bulkheads
Weekend 7: Mar 14
topshell layup
canopy layup
Week 8: Mar 16-20
Composites @ Pickle
have top shell bulkheads ready
Weekend 8: Mar 21
Composites @ Rob Edwards
demold + top shell bulkhead installation
demold + trim canopy
Week 9: Mar 23-27
Composites @ Rob edwards
Trim topshell
Weekend 9: Mar 28
Top shell and canopy completed and sent to be wrapped
Week 10: Mar 30-Apr 3
Continue
Weekend 10: Apr 4
Composites @ Rob Edwards
Things to add
livery timeline
mid march, bottom shell livery approved → bottom shell reinforcements installed and bs trimmed
talk to tiffany about who we’re going with and ask for lead time + tell annika + evan
by end of march, livery on car
top shell bulkheads
bubbles
canopy layup and mold prep
enclosure layups (2)
bellypan
firewall
wheel hole covers
bottom shell reinforcement installations
Livery
by next week, quotes for livery places, finalized place
lead time
does livery need to be approved by anyone? - approved by annika sullivan (source dat from combustion cr), approved by kayla
figure out details of wrapping both shell pieces
top shell mold prep
assemble, spackle, sand
chemical spray
sand
chemical spray
sand, prep/cut material
layup pt 1
prep/cut material
layup pt 2
demold, ts bulkheads
canopy
print mold
finished mold
get coat
sand
cut material
layup
demold + trim