Composites Manufacturing Projects and Tentative Timeline
Top Shell
Bottom Shell
Middle Shell
Canopy
Wheel Covers
Bulkheads (4 wd)
Battery Box (spring break?)
Battery box dividers (Spring Break?)
HV Enclosure - If this goes well maybe manufacture all enclosures if thats easier for emech (1-2 midweek + 1 wd)
Steering Wheel (3 wd)
Belly Pan (2-3 wd depending on size, done concurrently with seat)
Seat (2-3 wd depending on size, done concurrently with belly pan)
Daybreak Bulkheads
Pushrods (2-3 midweek (depends on how many test batches we do))
Frame Test Panels (2-3 wd depending on amount)
Dashboard (1wd)