Issues

  • waiting on OLA between ITS Systems and Applications
    • discussed with Jenn, she will be distributing a virtual server spreadsheet to select members of WOT to assist with filling out
    • see status report
  • discussed new completion date with client for Economics project, he was non-committal during conversation – waiting on confirmation of date

Highlights/Milestones

  • database authorizations for UTForge Subversion repositories ready for testing ahead of next week's Python/Django training

Upcoming

  • new timeline for Economics project
  • update packages and upgrade kernel for WOT virtual servers