Issues

  • waiting on OLA between ITS Systems and Applications

    • Jenn has distributed virtual server spreadsheet – see upcoming

    • see older status report

  • discussed new completion date with client for Economics project, he was non-committal during conversation – waiting on confirmation of date

Highlights/Milestones

  • replacing file-based to database authorizations for UTForge Subversion repositories

    • UPDATE:

      • finished with modifications to Trac plugin to match mod_authz_svn_db schema

      • finished with logic that deals with recursive directory bit

    • need to make modifications to classes used by PyPE as well as during project creation and deletion

Upcoming

  • finish UTForge database authorizations

  • complete task transition document

  • fill out virtual server spreadsheet

  • determine Systems/Apps/Help Desk split for WOT-Hosting sub-team services

  • new timeline for Economics project

  • update packages and upgrade kernel for WOT virtual servers

  • draft of task transition document for WOT Hosting sub-team services: