January 31 - February 4
Time sheet attached
Notes:
- PyPE
- discussion with Gary regarding responsibilities for data center move scheduled for March 12
- brief overview of architecture, what needs to be done
- explanation of documentation, where it is found, how it is organized
- discussion with Gary regarding responsibilities for data center move scheduled for March 12
- JIRA
- answering questions regarding new instance request from Center for Teaching and Learning
- discussion with Larry regarding our team's bandwidth in handling new instances
- subsequent discussion with Simi regarding options for CTL in regards to new JIRA installation
- other customer support and correspondence
- answering questions regarding new instance request from Center for Teaching and Learning
- UTForge
- granting permissions to Larry for projects he manages but does not have access to
- correspondence with user seeking developer entitlement; granting membership
- tracking down out of memory error on one of the VMs
- other user support, correspondence
- Wikis
- reviewing tickets in Footprint
- Economics Java application
- application development
- discussion with Oliver regarding Java database and socket communication efficiencies
- Miscellaneous
- discussion with Jack regarding DEV entitlement and requirements needed to keep the entitlement active
- my group membership was revoked yesterday, I am trying to make sure I understand why to avoid in the future
- reviewing and updating product/service line descriptions for Julienne
- assisting Margaret Myrick with server installation
- all hands meeting – meet the director
- informal meeting with Jenn regarding previous leave
- retrieving raised laptop base from desktop support
- meeting with HR regarding Family Leave policy
- time entry
- snow day
- sick day
- general (unable to categorize) e-mail reading and responses
- discussion with Jack regarding DEV entitlement and requirements needed to keep the entitlement active