July 8 - 14

July 8 - 14

Configurable software for matrix-based, multi-user, Economics Experiments

Complete:
  • developed the communication protocol that will be used by the clients and server to communicate status of tasks and synchronize dispersal of additional tasks.
  • meeting with John Lovelace regarding status of contract, remaining work
Upcoming:
  • determine new timeline for project
  • continue development; I am roughly half-way through the contract (original estimate 175.2 total hours)

UTForge

Complete:
  • correspondence with Biomedical Informatics Lab regarding version control, their needs
  • stewardship duties, reviewing and responding to e-mail from admin list
Upcoming:
  • declare a maintenance period to deploy Apache module (mod_authz_svn_db) and UTForge code changes to production virtual servers
  • shift virtual server administration duties to ITS Systems

JIRA

Complete:
  • provided additional LCM logs from pilot instance to OSFS and SIS
  • reviewed and responded to e-mail from admin list
Upcoming:
  • determine who owns and is backup for JIRA
  • shift virtual server administration duties to ITS Systems
  • move all instances of JIRA to RedHat VMs (currently on Windows VMs)

University Wiki Service (UWS)

Complete:
  • reviewed e-mail from admin list
Upcoming:
  • determine who is backup for UWS

Contracts' Virtual Server Administration:

Upcoming:
  • determine what applications currently on capps should migrate to totoro (new Contracts' applications virtual server)
    • determine who will do the migration
  • shift virtual server administration duties to ITS Systems

PyPE

Complete:
  • reviewed and responded to e-mail from admin list

Miscellaneous

Complete:
  • on leave for 1 day
  • interviewer for SSE position on team
  • ITS Systems town hall meeting
  • P&M team meeting
Upcoming:
  • complete virtual server spreadsheet provided by Jenn Coast – this is the next step in accomplishing the shift of virtual server administration duties to ITS Systems